case studies
Noise abatement
The Technology Hub will be built within a new building planned near the airport complex boundary. For this airport area, a transition zone is introduced:
- From airport zone to Class II zone, with plant operating 24 hours a day
Our design and production studio covered the following rooms:
- 01.Cogeneration unit with 901 kW electrical power and 536 kW thermal recovery power
- 02.Recovery boilers
- 03.Chiller units
- 04.Transformer room
The acoustic climate emerged after a measurement campaign carried out by our client’s competent acoustic technicians provided an average daytime level of 68.7 dBA and a nighttime level of 62.1 dBA.
The acoustic impact assessment, taking the minimum residual levels as a reference, resulted in 56 dBA for the daytime period and 46.3 dBA for the nighttime period.
To calculate the contribution of the sound sources within the Technology Hub, the noise emissions of the machinery and the acoustic facade insulation provided by the external walls were taken into account.
Solution
How did we achieve the expected values?
First, we treated the cogeneration room: we created an intake and exhaust ventilation system on the roof, dimensioned based on the engine characteristics, to guarantee a noise level of 55 dB(A) at 7 m, while the triple-seal opening has a sound insulation power of Rw 39 dB.
We studied and created a ventilation system for the transformer room with exhaust and soundproofed openings with acoustic louvers, for an attenuation of 20 dB(A).
In order to guarantee compliance with the zone limits, we also treated the rooftop systems by installing our sound-absorbing panels with a sound insulation power of Rw 34 dB along the entire perimeter of the concrete building.
Results
Results
Following the soundproofing intervention, we managed to guarantee an external noise level of 55 dB(A) at 10 m from the plant.
Thanks to the synergy established with our client’s technicians, the punctual and precise exchange of information, on-site verification with targeted inspections, design verification, and the shared schedule that defined the installation phases, we guaranteed the success of the project, safely and respecting all the timelines of the work phases.